INTERNAL / DRAFTOperations·Engineering & support

End-to-end acceptance and handover test plan

Purpose

Before this guide becomes the team's operating standard, run a repeatable end-to-end test using non-production data and approved accounts.

Test scenarios

ID Scenario Expected evidence Outcome to record
AT-01 Authorized GitLab login Dashboard loads as correct named account Pass/Fail
AT-02 Least-privilege project access Allowed project visible; unrelated private project denied Pass/Fail
AT-03 Create internal ticketing user User appears with expected role and project scope Pass/Fail
AT-04 Create restricted customer Customer sees only entitled products Pass/Fail
AT-05 Create product/version/release test record Correct options appear in ticket workflow Pass/Fail
AT-06 Customer creates support ticket Unique ticket ID appears in own list Pass/Fail
AT-07 Support assigns an engineer Assignment persists in admin portal Pass/Fail
AT-08 Backend GitLab handoff Exactly one matching item in mapped project with expected assignee Pass/Fail
AT-09 Engineer opens issue/repository Correct project and access Pass/Fail
AT-10 Support/customer replies Conversation history updated correctly Pass/Fail
AT-11 Email events enabled Creation/reply/assignment/closure messages, as configured Pass/Fail
AT-12 Secure patch upload/download Entitled test customer downloads correct checksum-matched file Pass/Fail
AT-13 Unauthorized patch/ticket access Unauthorized test user is denied Pass/Fail
AT-14 Ticket closure/reopen Correct portal state; actual GitLab behavior documented Pass/Fail
AT-15 PAT expired or project mapping invalid Safe failure, actionable logs and no unintended duplicate issue Pass/Fail
AT-16 Backup restoration rehearsal Restored approved test data usable Pass/Fail

Test record form

For each test capture tester, date, system build/version, test identity, test data ID, observed result, sanitized evidence location, approver and remediation issue if failed.

Sign-off criteria

All access isolation, token management, backup and patch handling tests should pass before a wider internal rollout. Open or failed scenarios require an owner and remediation date; do not silently mark inferred features as verified.